|
The Town of Smithfield’s
Department of Public Works has constructed a sand/salt storage facility on
the grounds of the existing highway department property. The purpose of
the salt storage facility is to house sand and salt year round and keep it
covered from the elements, such as rain and snow.
Recently the United
States Environmental Protection Agency, US EPA, regulated that all
municipalities, state and federal agencies have proper storage for their
sand and salt stockpiles used for road treatment during winter months.
During 2000, the town’s
Public Works, Engineering and Planning Departments sought out grant money
with the Rhode Island Department of Environmental Management, (RI DEM),
and the US EPA to offset the cost to construct such a facility. The town
signed a grant agreement with these two agencies consisting of items the
town must complete in order for the federal government to aid in paying
for $66,000 of the total construction cost of the salt storage facility.
The facility is now complete!

The Public Works
Department anticipates having the sand/salt loaded into the structure
sometime in the summer of 2002.
The project was started
with the help of some local agencies such as, The Woonasquatucket
Watershed Council, the Smithfield Conservation Commission and the
Department of Environmental Management. The project really gained
momentum when each of the agencies visited the site and saw what impacts
the Public Works Facility grounds was having on nearby wetlands. Rainfall
that collects from all of the buildings and pavement areas on the property
forms a gulley that constantly erodes a channel of earth into the
wetlands. Once it was apparent the effects the erosion was having on the
wetlands, a plan for action was devised. Spearheaded by former Assistant
Town Engineer, Joseph A. Casali, P.E., Town Engineer, Richard B. Geldard,
P.E., Deputy Public Works Director, Robert N. Lamoureux and the current
Assistant Town Engineer, Kevin Cleary, E.I.T., a plan was devised to cover
all of the sand/salt storage on the site at that time.

The Public Works
Department broke ground during January of 2002, after signing an Agreement
with the State in the fall of 2000.
The first task was to
remove the existing 60,000 tons of sand and gravel that was present on the
site and temporarily relocate some of the material.

The next task was to
grade the lot in such a manner that would allow the velocity of the runoff
to be significantly reduced during rainstorm events.

Not long after the lot
was leveled and graded, the department noticed a decrease in the amount of
storm water that was going to the wetlands, and they also realized that a
significant amount of sediments entering the wetlands had also been
reduced. After the lot had been graded and compacted, the Public Works
Department was ready to prepare the base for the salt storage facility.
Public Works prepared the ground by installing an asphalt pad for the
contractor to build the structure on.

Once the asphalt pad was
paved, the center location for the salt storage facility was chosen.
Construction began in June of 2002.

The contractor began
setting up the reinforcement steel for the concrete foundation wall and
not long after that the foundation walls were finished and the roof of the
structure was well under way.

The complete salt storage
facility has a covered dome shaped roof complete with an entry way large
enough for a front end loader, a ventilation fan and electrical lighting
for night-time visibility. The facility will house road salt keeping it
covered from the elements and also keeping if out of the groundwater and
wetlands.
During 2001, Deputy
Public Works Director, Robert N. Lamoureux, Assistant Town Engineer, Kevin
Cleary, E.I.T. and Town Planner, Christopher V. Hawkins applied for
another grant of $72,000 with US EPA and RI DEM under the Non-Point Source
Program to further complement the salt storage facility.

The purpose of this grant
is to install a complete closed drainage system consisting of
approximately a dozen catch basins, an oil/water/sediment separator and a
drainage detention pond that will control the runoff generated from the
site and allow it to discharge into the wetlands at a controlled rate and
also much cleaner than how it enters the wetlands today. Upon final
completion of the grant Agreement with the state and federal governments,
the Public Works Department will begin construction on this drainage
system and the Highway Garage Facility will be in complete compliance with
federal EPA and the state DEM regulations.
The last portion of the
drainage project will be a full wetland restoration project which will
consist of removing years of sediment from the wetland complex and the
surrounding buffer area and then re-vegetating the impacted area that has
been subject to years of uncontrolled runoff discharge.
The purpose of the overall Public Works
Facility plan is to improve water quality within the Woonasquatucket
Watershed by reducing sediments, water bound pollutants and other debris
from enter Smithfield’s waterways and possibly contaminating mankind’s
most valuable resource-water. If you are interested in accessing
more information about the Public Works Facility or volunteering in the
wetlands restoration project you can contact either Jim Suzman at 233-1034, or
Seth Lemoine at 233-1041.

|